General information
-
Phases
Phases Date phase valid fromDate phase valid toPhase29.02.200829.02.2012INITIAL01.03.201228.02.2014INITIAL EXTENDED01.03.201428.02.2015INITIAL EXTENDED01.03.201528.02.2016INITIAL EXTENDED29.02.201628.02.2017INITIAL EXTENDED -
Licensees – current
Licensees – current Date valid fromCompany longnameInterest [%] -
Operatorship – current
Operatorship – current Date valid fromCompany longname -
Area – current
Area – current Date valid fromBlock namePolygon numberPolygon area
[km2]Vertical limitations -
Work program (initial phase)
Work program (initial phase) Work obligationDecisionTask statusExpiry dateWellbore if drilledSeismology - collecting, reprocessing, interpretationApprovedStudy of geology and geophysicsApprovedDrillingApproved6407/1-6 S(BoV) Decision to continueDropped28.02.2016(PDO) Decision to submit plan for developmentDropped28.02.2017Decision to enter extension periodDropped28.02.2017 -
Conditions (production phase)
Conditions (production phase) Work taskDecisionDescription (norwegian)Task statusExpiry date -
Mortgages from the Petroleum register – current (in Norwegian only)
Mortgages from the Petroleum register – current (in Norwegian only) Dokument nummerRegistreringsdatoUtdrag av dokument589418.07.2011Faroe Petroleum Norge AS pantsetter sin 30 % deltakerandel i utvinningstillatelsen til fordel for BNP Paribas. Første prioritet panteobligasjon stor NOK 1,200,000,000, skriver norske kroner enmilliardertohundre millioner 00/100. Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver. Olje- og energidepartementet har i brev av 8.6.2011 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant.745509.12.2013Reduksjon av pantsettelse, første prioritet, dok. nr. 5894 registrert 18.7.2011i Faroe Petroleum Norge AS sin deltakerandel i utvinningstillatelsen fra 30 % til 20 %. Panthaver BPN Paribas samtykker til reduksjon av pant i brev datert 3.9.2013807723.09.2014Faroe Petroleum Norge AS pantsetter (tilleggspant) sin 20 % deltakerandel i utvinningstillatelsen til fordel for BNP Paribas. Første prioritet pantobligasjon stor NOK 1 200 000 000, skriver norske kroner en milliard to hundre millioner. Pantsetter har ikke rett til å overdra eller foreta ytterligere pantsettelser av pantsatte objekt uten skriftlig samtykke fra panthaver. Olje- og energidepartementet har i brev av 11.9.2014 gitt samtykke i medhold av petroleumsloven § 6-2 første ledd. Pantsettelsen utgjør et såkalt krysspant -
Wellbores – exploration, drilled in the production licence
Wellbores – exploration, drilled in the production licence Wellbore nameEntered dateCompleted datePurposeContent07.12.201224.01.2013WILDCATGAS/CONDENSATE01.02.201422.03.2014WILDCATGAS/CONDENSATE22.03.201420.04.2014APPRAISALGAS/CONDENSATE -
Wellbores – development, drilled in the production licence
Wellbores – development, drilled in the production licence Wellbore nameEntered dateCompleted datePurpose - planned -
Licensees – full history
Licensees – full history Date valid fromDate valid toCompany longnameInterest [%]10.09.201528.02.201635.00000020.00000020.00000015.00000010.00000021.11.201309.09.201535.00000020.00000020.00000015.00000010.00000030.06.201320.11.201335.00000030.00000020.00000015.00000024.03.201229.06.201350.00000030.00000020.00000030.09.201123.03.201250.00000030.00000020.00000001.01.201029.09.201130.00000025.00000020.00000015.00000010.00000017.01.200931.12.200940.00000030.00000020.00000010.00000001.01.200916.01.200930.00000030.00000020.00000010.00000010.00000029.02.200831.12.200830.00000030.00000020.00000020.000000 -
Operatorship – full history
Operatorship – full history Date valid fromDate valid toCompany longname24.03.201228.02.201617.01.200923.03.201229.02.200816.01.2009 -
Area – full history
Area – full history Date valid fromDate valid toBlock namePolygon numberPolygon area
[km2]Vertical limitations29.02.200828.02.20166406/32506407/11102 -
Licensees – transfers
Licensees – transfers Date valid fromTransfer directionType of changeCompany nameTransferred interest [%]10.09.2015FROMCHANGE OF COMPANY NAME10.000000TOCHANGE OF COMPANY NAME10.00000021.11.2013FROMTRANSFER10.000000TOTRANSFER10.00000030.06.2013FROMTRANSFER15.000000TOTRANSFER15.00000024.03.2012TOCHANGE OF COMPANY NAME50.000000FROMCHANGE OF COMPANY NAME50.00000030.09.2011FROMTRANSFER10.000000FROMTRANSFER15.000000TOTRANSFER25.00000001.01.2010FROMTRANSFER15.000000TOTRANSFER15.00000017.01.2009TOCHANGE OF COMPANY NAME30.000000FROMCHANGE OF COMPANY NAME30.00000001.01.2009FROMTRANSFER10.000000TOTRANSFER10.000000 -
Status reports
Status reports Document nameDocument formatDocument size [MB].pdf3.15